ASME B16.47
Inspection & Test Plan

ASME B16.47 Inspection & Test Plan (ITP)

A typical stage-wise ITP / quality plan for valves supplied to ASME B16.47 — inspection activities, tests, acceptance references and verifying documents, with recommended hold, witness and review points for QC and third-party inspection.

What is the ITP for ASME B16.47 valves?

An Inspection & Test Plan (ITP) sequences every check between raw material and dispatch, and assigns each an inspection level — Review (document check), Witness (inspector may attend), or Hold (work stops until released). The plan below is a typical ITP for valves built to ASME B16.47 (Large Diameter Steel Flanges NPS 26 Through NPS 60 Metric/Inch Standard); the tests and documents are drawn directly from the standard's requirements. Use it to structure your QAP or coordinate third-party inspection.

Inspection level:ReviewWitnessHold

1. Documentation & design review

Review
  • Approval of drawings, datasheets and QAP against ASME B16.47
  • Two non-interchangeable series: Series A (MSS SP-44 heritage) and Series B (API 605 heritage)
  • Pressure classes covered: Class 75 (Series A only), 150, 300, 400, 600, 900

2. Raw material verification

Review
  • Material Test Reports (MTRs) review per EN 10204 3.1/3.2
  • Positive Material Identification (PMI) of pressure-containing parts

3. Dimensional inspection

Witness
  • Dimensional check per ASME B16.47 / ASME B16.34 / applicable face-to-face
  • Wall thickness verification

4. NDE (as applicable)

Witness
  • Visual, and RT/UT/MPI/DPT of castings/welds per specification

5. Pressure & performance testing

Hold
  • Dimensional inspection per ASME B16.47 Series A or B tables
  • Hydrostatic shell test at 1.5× rated pressure for flanged valves
  • PMI verification for alloy steel and stainless steel flanges

Primary hold point — witnessed shell, seat and backseat tests.

6. Marking, painting & preservation

Review
  • Nameplate & body marking verification
  • Painting/coating DFT check, end protection and preservation

7. Final documentation

Hold
  • ASME B16.47 Series designation (A or B) on documentation and marking
  • Pressure class marking on flange
  • Material Test Reports (MTR) per EN 10204 3.1
  • Dimensional inspection report confirming series and class compliance

Final documentation review before release/dispatch.

This is a typical ITP framework populated from ASME B16.47 requirements, for reference. The actual hold/witness/review split is agreed per project between purchaser, manufacturer and the third-party inspection agency in the approved QAP. Confirm project-specific requirements before use.

Reviewed by Valve Standards Engineering, Vajra Industrial SolutionsDiscipline: Industrial Valve Standards & ComplianceLast reviewed: 20 June 2026

Connected Engineering

Need ASME B16.47 valves with a full ITP?

We supply ASME B16.47-compliant valves with a project-specific ITP, in-house QC and third-party inspection (SGS, BV, TUV, DNV) coordination — hold and witness points accommodated. Get a 24-hour quote.

Engineering references