Back to Resources

Shutdown & Turnaround Valve Checklist

Planned Outage Procurement Worksheet — Print or save as PDF

Vajra Industrial Solutions
SHUTDOWN & TURNAROUND VALVE CHECKLIST
Planned Outage Procurement & Installation Worksheet
Doc: VIS-TAR-004 Rev.01
Plant / Unit: ____________
TAR Date: ______________
Prepared By: ___________

URGENCY CLASSIFICATION & EMERGENCY SOURCING TRIGGERS

Trigger ConditionUrgency LevelTarget Lead Time
Active external leakage (packing or body joint)Immediate — Emergency sourcing24–72 hours
Failed seat test — passing to downstreamPriority — same shutdown window1–5 days
Seized / failed to operate on demandPriority — same shutdown window1–5 days
Visible cracks or major corrosion on bodyHigh — before next startup1–2 weeks
Class A / safety-critical valve approaching inspection intervalPlan ahead — order with 12-week lead12–20 weeks
Class B / process-critical — 2+ failures in rolling yearPlan for next TAR8–16 weeks
Class C / utility — minor leakage manageableNext TAR or planned outage4–12 weeks

Contact: sales@vajravyuh.com | WhatsApp: +91 9979774557 | Emergency sourcing response within 4 hours

PHASE 1 — PRE-SHUTDOWN AUDIT (12–24 Weeks Before TAR)
#TaskDoneNotes / Tag Reference
1Extract valve asset register from CMMS — all valves in scope
2Review valve inspection history — flag items with recurring failures
3Review last shutdown NCR (non-conformance reports) for valves
4Walk the plant — physically inspect valve condition (stem, packing, handwheel)
5Identify valves with visible external corrosion, leaking packing, or seizure risk
6Check valve positions on P&IDs — verify size, class, service fluid
7Classify each valve: Replace / Repair / Inspect / Monitor
8Identify safety-critical valves (PSV, ESD, blowdown) — mandatory inspection
9Flag any valves on regulatory inspection schedule (IBR, PESO, statutory)
10Review utility valve status — cooling water, steam, air isolation valves
PHASE 2 — SPARE CLASSIFICATION & CRITICALITY RATING (10–20 Weeks Before TAR)
#TaskDoneNotes / Tag Reference
1Assign criticality: A = Safety-critical (PSV/ESD), B = Process-critical, C = Utility
2Check warehouse stock — existing spare valves / repair kits available
3Identify long-lead items (alloy bodies, Class 900+, actuated packages)
4Place orders for long-lead items immediately (12–24 week lead time typical)
5Raise RFQs for standard replacement valves (API 6D, BS EN, IS standard)
6Confirm vendor lead times and delivery schedule vs. TAR start date
7Request Mill Test Certificates (EN 10204 3.1) at time of order — not after delivery
8Identify valves requiring TPI witness (Class B / A criticality)
9Arrange third-party inspection agency for FAT if required
10Confirm IBR Form III-C / III-E for steam service replacements
PHASE 3 — RECEIVING & PRE-INSTALLATION INSPECTION (2–4 Weeks Before TAR)
#TaskDoneNotes / Tag Reference
1Receive valves — verify packing list against purchase order
2Check for visible transit damage — dents, cracked handwheels, bent stems
3Verify material markings on body: material grade, class, NPS, heat number
4Verify MTC heat numbers match valve body stamping (traceability check)
5Verify face-to-face dimension against ASME B16.10 table
6Verify end connection facing (RF/RTJ/BW) matches P&ID spec
7Check valve operation — open/close with no binding before storage
8Store valves in dry, covered location with end caps fitted
9Tag each valve with P&ID tag number and TAR work order number
10File all documentation (MTC, test certs, IBR forms) in project folder
PHASE 4 — INSTALLATION SCOPE (During TAR)
#TaskDoneNotes / Tag Reference
1Remove old valve — photograph in-situ before removal (record condition)
2Inspect piping flange faces for corrosion, pitting, or damage
3Clean flange faces — remove old gasket material entirely
4Verify new valve bore is clear — no packing, shipping covers, or debris
5Install correct gasket type (spiral wound, Kammprofile, PTFE) per P&ID
6Torque flange bolts per ASME PCC-1 torque table and pattern (cross pattern)
7Verify valve stem orientation — rising stem visible after installation
8Verify direction arrow (flow direction) for check valves
9Install packing correctly — do not over-tighten gland; leave room for live-loading
10Functional test after installation — operate 3 times before system pressurisation
PHASE 5 — POST-INSTALLATION PRESSURE TEST & HANDOVER
#TaskDoneNotes / Tag Reference
1Conduct line pressure test — leak test all new flange joints with soapy water or N2
2Verify seat tightness — check for leakage across closed valve
3Verify packing is not leaking at operating conditions
4Update P&ID redline — mark replaced valves as 'New'
5Update CMMS / asset register with new valve serial number and installation date
6File installation records, torque records, and pressure test results
7Return all MTCs and test certificates to plant documentation system
8Raise NCR if any defects found during installation — photograph and document
9Close out TAR work order — sign off completion
10Update next inspection schedule in CMMS (typically 4 years for most process valves)

VALVE REPLACEMENT LOG

P&ID TagServiceNPS / ClassOld MaterialNew PO No.SupplierMTC Recv.Installed ByDate
VIS-TAR-004 Rev.01 — Vajra Industrial Solutions — www.vajravyuh.comEmergency: +91 9979774557 | sales@vajravyuh.com

Emergency valve sourcing

For urgent valve replacement during shutdown — contact Vajra for same-day quote response and priority dispatch from stock.