NACE MR0175 / ISO 15156
Inspection & Test Plan

NACE MR0175 / ISO 15156 Inspection & Test Plan (ITP)

A typical stage-wise ITP / quality plan for valves supplied to NACE MR0175 / ISO 15156 — inspection activities, tests, acceptance references and verifying documents, with recommended hold, witness and review points for QC and third-party inspection.

What is the ITP for NACE MR0175 / ISO 15156 valves?

An Inspection & Test Plan (ITP) sequences every check between raw material and dispatch, and assigns each an inspection level — Review (document check), Witness (inspector may attend), or Hold (work stops until released). The plan below is a typical ITP for valves built to NACE MR0175 / ISO 15156 (Petroleum and Natural Gas Industries - Materials for Use in H₂S-Containing Environments (Sour Service)); the tests and documents are drawn directly from the standard's requirements. Use it to structure your QAP or coordinate third-party inspection.

Inspection level:ReviewWitnessHold

1. Documentation & design review

Review
  • Approval of drawings, datasheets and QAP against NACE MR0175 / ISO 15156
  • Carbon steel (A216 WCB, A105): maximum hardness 22 HRC (PWHT required for cast bodies)
  • Low-alloy steels: individual hardness limits per NACE Table B.1

2. Raw material verification

Review
  • Material Test Reports (MTRs) review per EN 10204 3.1/3.2
  • Positive Material Identification (PMI) of pressure-containing parts

3. Dimensional inspection

Witness
  • Dimensional check per NACE MR0175 / ISO 15156 / ASME B16.34 / applicable face-to-face
  • Wall thickness verification

4. NDE (as applicable)

Witness
  • Visual, and RT/UT/MPI/DPT of castings/welds per specification

5. Pressure & performance testing

Hold
  • Hardness testing: all valve bodies, bonnets, stems - per NACE MR0175 limits
  • Charpy impact testing (where required by NACE MR0175)
  • Weld hardness survey for hard-faced seats
  • PWHT verification (where required)

Primary hold point — witnessed shell, seat and backseat tests.

6. Marking, painting & preservation

Review
  • Nameplate & body marking verification
  • Painting/coating DFT check, end protection and preservation

7. Final documentation

Hold
  • NACE MR0175 compliance certificate on valve data sheet
  • Hardness test records (Brinell or Rockwell) for all CRAs and CS components
  • PWHT records (time-temperature charts)
  • Welding procedure qualification records (WPQRs) with NACE hardness compliance

Final documentation review before release/dispatch.

This is a typical ITP framework populated from NACE MR0175 / ISO 15156 requirements, for reference. The actual hold/witness/review split is agreed per project between purchaser, manufacturer and the third-party inspection agency in the approved QAP. Confirm project-specific requirements before use.

Reviewed by Valve Standards Engineering, Vajra Industrial SolutionsDiscipline: Industrial Valve Standards & ComplianceLast reviewed: 20 June 2026