Lifecycle Playbooks
Stage 11 · Planned outage (TA/shutdown window)

Shutdown & Turnaround Valve Scope

Valves are a classic turnaround critical path: identified late, ordered late, delivered late. This playbook front-loads the valve scope so the window is spent installing, not expediting.

For: Turnaround planners and shutdown procurement

You are here if

  • The TA valve list is due and the walkdown has not happened
  • Long-lead valve deliveries threaten the shutdown critical path
  • Mid-shutdown discoveries need valves in days, not weeks

Where this stage goes wrong

  • Valve scope frozen from inspection wish-lists without a physical walkdown
  • Long-lead items (alloy, large-bore, actuated) discovered inside the procurement lead time
  • No standby source for mid-shutdown discoveries, converting findings into extensions

The Playbook

  1. 1Walk down the scope earlyPhysical verification of every candidate tag months out - type, size, class, material, ends - kills spec surprises.
  2. 2Split the list by lead timeAlloy, large-bore and actuated tags order first; commodity carbon-steel valves can trail.
  3. 3Order against the shutdown date, not the need dateDelivery with margin before mobilisation; witnessed testing planned so certificates do not trail the valves.
  4. 4Pre-agree an emergency sourceA supplier with stock and a 24-hour quote path for mid-TA discoveries is shutdown insurance - agree it before the window.
  5. 5Stage, verify and issue by systemValves received, documents married, staged by system and issued to the schedule - not hunted in laydown mid-window.

Stage deliverables

Walked-down TA valve listLead-time-split procurement planEmergency sourcing agreement
Reviewed by Process Engineering, Vajra Industrial SolutionsDiscipline: Valve Service SpecificationLast reviewed: 20 June 2026

In this stage right now?

Our engineers work this stage daily - send your situation and get specification, sourcing or inspection support with a 24-hour response.