ASME B16.5 Inspection & Test Plan (ITP)
A typical stage-wise ITP / quality plan for valves supplied to ASME B16.5 — inspection activities, tests, acceptance references and verifying documents, with recommended hold, witness and review points for QC and third-party inspection.
What is the ITP for ASME B16.5 valves?
An Inspection & Test Plan (ITP) sequences every check between raw material and dispatch, and assigns each an inspection level — Review (document check), Witness (inspector may attend), or Hold (work stops until released). The plan below is a typical ITP for valves built to ASME B16.5 (Pipe Flanges and Flanged Fittings NPS 1/2 through NPS 24 Metric/Inch Standard); the tests and documents are drawn directly from the standard's requirements. Use it to structure your QAP or coordinate third-party inspection.
1. Documentation & design review
Review- Approval of drawings, datasheets and QAP against ASME B16.5
- Seven pressure classes defined: Class 150, 300, 600, 900, 1500, and 2500
- Thirty-three material groups (1.1 through 3.3) each with its own P-T rating table
2. Raw material verification
Review- Material Test Reports (MTRs) review per EN 10204 3.1/3.2
- Positive Material Identification (PMI) of pressure-containing parts
3. Dimensional inspection
Witness- Dimensional check per ASME B16.5 / ASME B16.34 / applicable face-to-face
- Wall thickness verification
4. NDE (as applicable)
Witness- Visual, and RT/UT/MPI/DPT of castings/welds per specification
5. Pressure & performance testing
Hold- Shell hydrostatic test: 1.5× rated pressure per class and material group
- Flange facing dimensional inspection to B16.5 tolerances
- Positive material identification (PMI) for alloy and stainless steel flanges
Primary hold point — witnessed shell, seat and backseat tests.
6. Marking, painting & preservation
Review- Nameplate & body marking verification
- Painting/coating DFT check, end protection and preservation
7. Final documentation
Hold- ASME B16.5 compliance marking on valve body flange
- Material Test Reports (MTR) per EN 10204 3.1
- Pressure-temperature rating data sheet referencing B16.5 material group
- Hydrostatic test certificate
Final documentation review before release/dispatch.
This is a typical ITP framework populated from ASME B16.5 requirements, for reference. The actual hold/witness/review split is agreed per project between purchaser, manufacturer and the third-party inspection agency in the approved QAP. Confirm project-specific requirements before use.
Connected Engineering
Need ASME B16.5 valves with a full ITP?
We supply ASME B16.5-compliant valves with a project-specific ITP, in-house QC and third-party inspection (SGS, BV, TUV, DNV) coordination — hold and witness points accommodated. Get a 24-hour quote.