ASME B31.1 Inspection & Test Plan (ITP)
A typical stage-wise ITP / quality plan for valves supplied to ASME B31.1 — inspection activities, tests, acceptance references and verifying documents, with recommended hold, witness and review points for QC and third-party inspection.
What is the ITP for ASME B31.1 valves?
An Inspection & Test Plan (ITP) sequences every check between raw material and dispatch, and assigns each an inspection level — Review (document check), Witness (inspector may attend), or Hold (work stops until released). The plan below is a typical ITP for valves built to ASME B31.1 (Power Piping); the tests and documents are drawn directly from the standard's requirements. Use it to structure your QAP or coordinate third-party inspection.
1. Documentation & design review
Review- Approval of drawings, datasheets and QAP against ASME B31.1
- Valve design must comply with ASME B16.34 pressure-temperature ratings for the service class
- High-pressure steam valves: typically Class 1500 or Class 2500, Cr-Mo alloy steel body (WC6/WC9/P91)
2. Raw material verification
Review- Material Test Reports (MTRs) review per EN 10204 3.1/3.2
- Positive Material Identification (PMI) of pressure-containing parts
3. Dimensional inspection
Witness- Dimensional check per ASME B31.1 / ASME B16.34 / applicable face-to-face
- Wall thickness verification
4. NDE (as applicable)
Witness- Visual, and RT/UT/MPI/DPT of castings/welds per specification
5. Pressure & performance testing
Hold- Hydrostatic test of each valve per ASME B16.34 / API 598 before installation
- System hydrostatic or pneumatic test after installation per B31.1 test requirements
- NDE examination of welds (RT or UT) for Class 1 and critical piping
Primary hold point — witnessed shell, seat and backseat tests.
6. Marking, painting & preservation
Review- Nameplate & body marking verification
- Painting/coating DFT check, end protection and preservation
7. Final documentation
Hold- ASME B16.34 compliance marking on valve body
- Material Test Reports (MTR) per EN 10204 3.1 for alloy steel bodies
- Weld procedure specifications (WPS) and procedure qualification records (PQR) per ASME Section IX
- PWHT records for alloy steel valves and weld-end installations
- Pressure test certificate
Final documentation review before release/dispatch.
This is a typical ITP framework populated from ASME B31.1 requirements, for reference. The actual hold/witness/review split is agreed per project between purchaser, manufacturer and the third-party inspection agency in the approved QAP. Confirm project-specific requirements before use.