EN 1092-1
Inspection & Test Plan

EN 1092-1 Inspection & Test Plan (ITP)

A typical stage-wise ITP / quality plan for valves supplied to EN 1092-1 — inspection activities, tests, acceptance references and verifying documents, with recommended hold, witness and review points for QC and third-party inspection.

What is the ITP for EN 1092-1 valves?

An Inspection & Test Plan (ITP) sequences every check between raw material and dispatch, and assigns each an inspection level — Review (document check), Witness (inspector may attend), or Hold (work stops until released). The plan below is a typical ITP for valves built to EN 1092-1 (Flanges and Their Joints - Circular Flanges for Pipes, Valves, Fittings and Accessories, PN Designated - Part 1: Steel Flanges); the tests and documents are drawn directly from the standard's requirements. Use it to structure your QAP or coordinate third-party inspection.

Inspection level:ReviewWitnessHold

1. Documentation & design review

Review
  • Approval of drawings, datasheets and QAP against EN 1092-1
  • PN (Pressure Nominal) designations from PN 6 through PN 400 - each with defined P-T rating by material group
  • Flange type designations: Type 01 (plate, flat face), Type 02 (loose plate), Type 05 (blind), Type 11 (weld neck), Type 12 (hubbed slip-on), Type 13 (hubbed threaded), Type 21 (integral), Type 34 (welding boss)

2. Raw material verification

Review
  • Material Test Reports (MTRs) review per EN 10204 3.1/3.2
  • Positive Material Identification (PMI) of pressure-containing parts

3. Dimensional inspection

Witness
  • Dimensional check per EN 1092-1 / ASME B16.34 / applicable face-to-face
  • Wall thickness verification

4. NDE (as applicable)

Witness
  • Visual, and RT/UT/MPI/DPT of castings/welds per specification

5. Pressure & performance testing

Hold
  • Dimensional inspection of flange face, bolt circle, and outer diameter per EN 1092-1 tables
  • Shell hydrostatic test per manufacturer standard or PED requirements
  • Material verification: PMI or 3.1 MTR for alloy and stainless steel flanges

Primary hold point — witnessed shell, seat and backseat tests.

6. Marking, painting & preservation

Review
  • Nameplate & body marking verification
  • Painting/coating DFT check, end protection and preservation

7. Final documentation

Hold
  • EN 1092-1 dimensional compliance marking on flange
  • CE Declaration of Conformity under PED 2014/68/EU (for EU supply)
  • Material Test Report (MTR) per EN 10204 3.1
  • Dimensional inspection report

Final documentation review before release/dispatch.

This is a typical ITP framework populated from EN 1092-1 requirements, for reference. The actual hold/witness/review split is agreed per project between purchaser, manufacturer and the third-party inspection agency in the approved QAP. Confirm project-specific requirements before use.

Reviewed by Valve Standards Engineering, Vajra Industrial SolutionsDiscipline: Industrial Valve Standards & ComplianceLast reviewed: 20 June 2026