What is the ITP for EN 558 valves?

An Inspection & Test Plan (ITP) sequences every check between raw material and dispatch, and assigns each an inspection level — Review (document check), Witness (inspector may attend), or Hold (work stops until released). The plan below is a typical ITP for valves built to EN 558 (EN 558 - Face-to-Face and Centre-to-Face Dimensions of Metal Valves for Use in Flanged Pipe Systems); the tests and documents are drawn directly from the standard's requirements. Use it to structure your QAP or coordinate third-party inspection.

Inspection level:ReviewWitnessHold

1. Documentation & design review

Review
  • Approval of drawings, datasheets and QAP against EN 558
  • Series 1: short-pattern valves (butterfly wafer and lug, check valves)
  • Series 14: standard face-to-face for gate and globe valves to PN 16

2. Raw material verification

Review
  • Material Test Reports (MTRs) review per EN 10204 3.1/3.2
  • Positive Material Identification (PMI) of pressure-containing parts

3. Dimensional inspection

Witness
  • Dimensional check per EN 558 / ASME B16.34 / applicable face-to-face
  • Wall thickness verification

4. NDE (as applicable)

Witness
  • Visual, and RT/UT/MPI/DPT of castings/welds per specification

5. Pressure & performance testing

Hold
  • Dimensional inspection per EN 558 table at time of manufacture

Primary hold point — witnessed shell, seat and backseat tests.

6. Marking, painting & preservation

Review
  • Nameplate & body marking verification
  • Painting/coating DFT check, end protection and preservation

7. Final documentation

Hold
  • Dimensional inspection report confirming EN 558 series compliance

Final documentation review before release/dispatch.

This is a typical ITP framework populated from EN 558 requirements, for reference. The actual hold/witness/review split is agreed per project between purchaser, manufacturer and the third-party inspection agency in the approved QAP. Confirm project-specific requirements before use.

Reviewed by Valve Standards Engineering, Vajra Industrial SolutionsDiscipline: Industrial Valve Standards & ComplianceLast reviewed: 20 June 2026

Need EN 558 valves with a full ITP?

We supply EN 558-compliant valves with a project-specific ITP, in-house QC and third-party inspection (SGS, BV, TUV, DNV) coordination — hold and witness points accommodated. Get a 24-hour quote.

Engineering references