A typical stage-wise ITP / quality plan for valves supplied to ISO 15848-1 — inspection activities, tests, acceptance references and verifying documents, with recommended hold, witness and review points for QC and third-party inspection.

What is the ITP for ISO 15848-1 valves?

An Inspection & Test Plan (ITP) sequences every check between raw material and dispatch, and assigns each an inspection level — Review (document check), Witness (inspector may attend), or Hold (work stops until released). The plan below is a typical ITP for valves built to ISO 15848-1 (Industrial Valves - Measurement, Test and Qualification Procedures for Fugitive Emissions - Part 1); the tests and documents are drawn directly from the standard's requirements. Use it to structure your QAP or coordinate third-party inspection.

Inspection level:ReviewWitnessHold

1. Documentation & design review

Review
  • Approval of drawings, datasheets and QAP against ISO 15848-1
  • Tightness Class A: ≤1×10⁻⁴ mg/(s·m) - tightest class for LDAR programmes and EU BREF BAT compliance
  • Tightness Class B: ≤5×10⁻⁴ mg/(s·m) - intermediate class for most EU industrial valve specs

2. Raw material verification

Review
  • Material Test Reports (MTRs) review per EN 10204 3.1/3.2
  • Positive Material Identification (PMI) of pressure-containing parts

3. Dimensional inspection

Witness
  • Dimensional check per ISO 15848-1 / ASME B16.34 / applicable face-to-face
  • Wall thickness verification

4. NDE (as applicable)

Witness
  • Visual, and RT/UT/MPI/DPT of castings/welds per specification

5. Pressure & performance testing

Hold
  • Helium leak test at rated class temperature and pressure
  • Minimum 210 mechanical cycles (CO1) or 2,500 cycles (CO2) before qualification
  • Tightness measurement using mass spectrometry or equivalent helium leak detector

Primary hold point — witnessed shell, seat and backseat tests.

6. Marking, painting & preservation

Review
  • Nameplate & body marking verification
  • Painting/coating DFT check, end protection and preservation

7. Final documentation

Hold
  • ISO 15848-1 Type Test Certificate from accredited third-party laboratory
  • Tightness class (A/B/C), endurance class (CO1/CO2), and temperature class on certificate

Final documentation review before release/dispatch.

This is a typical ITP framework populated from ISO 15848-1 requirements, for reference. The actual hold/witness/review split is agreed per project between purchaser, manufacturer and the third-party inspection agency in the approved QAP. Confirm project-specific requirements before use.

Reviewed by Valve Standards Engineering, Vajra Industrial SolutionsDiscipline: Industrial Valve Standards & ComplianceLast reviewed: 20 June 2026