API 6FA
Inspection & Test Plan

API 6FA Inspection & Test Plan (ITP)

A typical stage-wise ITP / quality plan for valves supplied to API 6FA — inspection activities, tests, acceptance references and verifying documents, with recommended hold, witness and review points for QC and third-party inspection.

What is the ITP for API 6FA valves?

An Inspection & Test Plan (ITP) sequences every check between raw material and dispatch, and assigns each an inspection level — Review (document check), Witness (inspector may attend), or Hold (work stops until released). The plan below is a typical ITP for valves built to API 6FA (Specification for Fire Testing of Valves); the tests and documents are drawn directly from the standard's requirements. Use it to structure your QAP or coordinate third-party inspection.

Inspection level:ReviewWitnessHold

1. Documentation & design review

Review
  • Approval of drawings, datasheets and QAP against API 6FA
  • Fire exposure test: 750–1000°C for 30 minutes
  • External leakage through stem and body joints ≤200 mL/min during and after fire

2. Raw material verification

Review
  • Material Test Reports (MTRs) review per EN 10204 3.1/3.2
  • Positive Material Identification (PMI) of pressure-containing parts

3. Dimensional inspection

Witness
  • Dimensional check per API 6FA / ASME B16.34 / applicable face-to-face
  • Wall thickness verification

4. NDE (as applicable)

Witness
  • Visual, and RT/UT/MPI/DPT of castings/welds per specification

5. Pressure & performance testing

Hold
  • Fire test: 750–1000°C for 30 minutes in gas-fired or propane furnace
  • Post-fire leakage: seats ≤200 mL/min, stem/body ≤200 mL/min
  • Post-fire operation: full open/close cycle
  • Certificate of qualification (CoQ) required from third-party test facility

Primary hold point — witnessed shell, seat and backseat tests.

6. Fire-type test (qualification)

Hold
  • Fire test per API 607 / API 6FA with post-fire leakage acceptance

7. Marking, painting & preservation

Review
  • Nameplate & body marking verification
  • Painting/coating DFT check, end protection and preservation

8. Final documentation

Hold
  • API 6FA fire test certificate per model/size range
  • Third-party test laboratory certification
  • Bill of Materials confirming same construction as tested valve
  • Production test certificates (hydrostatic + seat)

Final documentation review before release/dispatch.

This is a typical ITP framework populated from API 6FA requirements, for reference. The actual hold/witness/review split is agreed per project between purchaser, manufacturer and the third-party inspection agency in the approved QAP. Confirm project-specific requirements before use.

Reviewed by Valve Standards Engineering, Vajra Industrial SolutionsDiscipline: Industrial Valve Standards & ComplianceLast reviewed: 20 June 2026